Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, MARCH 3, 2011

ALLIED HEALTH MITIGATION

  • The contractor continued to weld the structural steel for the new walkway storefront.  
  • Workers continued to tape and float the walls near the new auditorium. 
  • Additional network cabling is being pulled for the 1st Floor offices. 
  • The contractor continued installing doors in the 1st Floor offices.   

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued pulling feeder cable for the MDP-1 panel in the A-Tower.
  • Facility Services staff painted the walls of the laundry room in the A-Tower.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor placed concrete bases for three pumps on the mezzanine of the pump room.
  • A crew continued installing ceiling grid on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water and chilled water piping in the basement.
  • Underground electrical conduit was installed near the generator in the lakeside lot.
  • Workers continued installing electrical conduits along the Tulane side corridor on the 6th Floor to relocate panel EFC.

CSRB EXHAUST UPGRADE:

  • The contractor removed the steel supports for the plaster ceiling above the 1st Floor corridor.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued running heating hot water lines to the VAVs near the Gross Anatomy and Oral Pathology labs.  
  • They continued installing ductwork above the Oral Pathology labs.
  • The contractor insulated the new heating hot water and chilled water lines above Oral Pathology.
  • The control panels for the AHUs above Oral Pathology and Gross Anatomy were set.       

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING:

  • The contractor continued constructing partitions to cover 2 open bays on the west and east side of the Clinic Bldg and 2 open bays on the north side of the Admin Building. 

DENTAL CAMPUS STUDENT ATHLETIC FIELDS:

  • The contractor finished fine grading the clay for the softball infield.
  • The irrigation subcontractor installed pipe and quick disconnect fittings between both fields and the right field portion of the softball field.

DENTAL SCHOOL LIGHTING REPLACEMENT"

  • The contractor installed another 13 high-efficiency light fixtures on the 3rd Floor.