Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, MARCH 30, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the electrical box on the exterior of the building.
  • They installed light fixtures in the 2nd Floor corridors along Gravier Street.   
  • Crews continued welding structural steel below the walkway along the Gravier Street side of the building.   
  • The contractor continued installing glass partitions on the 1st Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed door hardware on the 1st Floor of the main building.
  • Crews ran and terminated wires for the temporary generator in preparation for the electrical shutdown tomorrow.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heat exchanger piping.
  • Workers continued shot-blasting the 1st Floor mail room in preparation for the epoxy flooring installation.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor poured concrete for the transformer vault wall in the basement.
  • They continued welding and installing 8-inch chilled water pipes in the basement.

CSRB EXHAUST UPGRADE:

  • The contractor removed exhaust ductwork from the 1st Floor feed room.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing control wires for the units near Oral Pathology and Gross Anatomy.   
  • The electrical contractor continued installing new electrical wire for the two units in the penthouse.
  • The contractor replaced the heating hot water riser on the B side of the 3rd and 4th Floors. 

DENTAL SCHOOL LIGHTING REPLACEMENT PROJECT:

  • The contractor replaced 19 light fixtures on the 3rd Floor of the Clinic Building.

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING:

  • The contractor continued installing new caulk on the cross-over section between the Clinic and Administration buildings.