Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, APRIL 20, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor welded the stairs for the new generator platform in place. 
  • Workers continued framing out the sheetrock fur down immediately inside of the new entryway on the 2nd Floor.     

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the interior CMU wall in the fire pump room on the 2nd level of the new building.
  • Exhaust fans were installed in the domestic water pump room and the generator room.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor began painting the exterior doors in the back of house area on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding and installing 8-inch chilled water lines in the basement.
  • They continued erecting concrete forms for the passenger elevators in the basement.
  • Crews continued installing electrical conduits on the 2nd and 3rd Floors.

CSRB EXHAUST UPGRADE:

  • The contractor continued insulating the ductwork branches for each Room included in Phase 1A.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued replacing ceiling tile and light fixtures for unit 8C. 
    • 12 fixtures have been installed on the 8th Floor of the Clinic Building. 

  • Crews continued installing the B-side heating hot water riser. The 3rd Floor riser has been installed. 
  • Workers continued removing ceiling tile, grid, and light fixtures for unit 8D. 
  • The asbestos contractor removed ductwork and installed collars for unit 8D on the 8th Floor. 
  • The contractor started installing spiral ductwork for unit 8A.

  • The contractor continued assembling and setting unit L3A in the Administration Building.     
  • They continued running spiral ductwork into Room 2102 (Parking Services) and through the Faculty Practice area on the 2nd Floor. 
  • The contractor set the VFDs for both units.   

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING:

  • The contractor continued removing old caulk and installing new backer rod and new caulk on the north side of the Clinic Building and east side of the crossover (between Administration & Clinic Buildings).

DENTAL CAMPUS PARKING LOT LIGHTING:

  • The contractor completed making the wiring connections for all 24 light poles and cleaned the construction site.