Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, APRIL 21, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the stairs for the new generator platform in place. 
  • They continued framing out the sheetrock fur down immediately inside of the new entryway on the 2nd Floor.     
  • The contractor removed a section of wall in 2nd Floor stairwell 1 to make a doorway into the new switchgear room. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing interior CMU wall in the fire pump room on the 2nd level of the new building.
  • The contractor installed fire alarm devices on the 2nd level of the new building.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued painting and installed door hardware on the 1st Floor exterior doors.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding and installing 8-inch chilled water lines in the basement.
  • They continued erecting concrete forms for the passenger elevators in the basement.
  • Workers continued relocating the sewer line near the loading dock.
  • The contractor removed existing electrical conduits from the basement.

CSRB EXHAUST UPGRADE:

  • The contractor completed insulating the ductwork branches for each room in Phase 1A.
  • The fire sprinkler heads were reinstalled in the 1st Floor corridor.
  • Crews began installing the ceiling supports in the 1st Floor corridor.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor installed 11 light fixtures on the 8th Floor of the Clinic Building. 
  • They continued installing the B-side heating hot water riser and installed the 2nd Floor riser. 
  • The asbestos contractor removed ductwork and installed collars for unit 8D on the 8th Floor. 
  • The contractor continued installing spiral ductwork and set four VAVs for unit 8A.
  • The contractor ran chilled water lines for L2A and L3A in the Administration Building. 
  • Crews continued running spiral duct work above Room 2102 (parking services). 

DENTAL CAMPUS PARKING LOT LIGHTING:

  • The contractor installed the waterproof enclosure and connected all underground conduits to the enclosure.