ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued roughing in the medical gas system for the 2nd Floor simulator rooms. 
  • Toilet partitions were installed in the Mens restroom on the 1st Floor. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor painted the exterior soffit on the 2nd Floor of the new elevated structure.
  • Thermostats were installed in both of the pump rooms and the generator room.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the water piping for the mop sink in the 2nd Floor housekeeping closet.
  • Steel decking was installed in the 2nd Floor pump room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical wires on the 2nd and 3rd Floors and removing abandoned conduits in the basement.
  • They continued installing chilled water lines in the basement.

CSRB EXHAUST UPGRADE:

  • The contractor painted the doorframe on the 1st Floor.
  • The floor penetrations for exhaust riser #4 were cut on the 4th, 5th, and 6th Floors.
  • Workers began relocating a roof drain on the 7th Floor.

CEB COVERED WALKWAY:

  • Approximately 80% of the curved top metal panels have been installed on canopy A at the Claiborne Street entrance to the Gravier Garage.
  • The contractor finished installing the corrugated roof decking on the long side and 1 of 2 short sides of canopy B beside the Medical School Building.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing rectangular supply ductwork and fresh air ductwork for unit 8A and heating water lines for units 8A and 8D in the Clinic Building.
  • They started running the main heating water lines for AHU 8A.
  • Crews insulated supply ductwork on the 8th Floor.       
  • The contractor continued installing reheat lines for VAVs in the Administration Building.  The contractor has now completed 11 of 14 VAVs. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continues removing old caulk and installing new caulk on the north and east sides of the Clinic Building and on the south side of the Administration Building.