TUESDAY, MAY 10, 2011
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued roughing in the medical gas system for the 2nd Floor simulator rooms.
- Toilet partitions were installed in the Mens restroom on the 1st Floor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor painted the exterior soffit on the 2nd Floor of the new elevated structure.
- Thermostats were installed in both of the pump rooms and the generator room.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor installed the water piping for the mop sink in the 2nd Floor housekeeping closet.
- Steel decking was installed in the 2nd Floor pump room.
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing electrical wires on the 2nd and 3rd Floors and removing abandoned conduits in the basement.
- They continued installing chilled water lines in the basement.
CSRB EXHAUST UPGRADE:
- The contractor painted the doorframe on the 1st Floor.
- The floor penetrations for exhaust riser #4 were cut on the 4th, 5th, and 6th Floors.
- Workers began relocating a roof drain on the 7th Floor.
CEB COVERED WALKWAY:
- Approximately 80% of the curved top metal panels have been installed on canopy A at the Claiborne Street entrance to the Gravier Garage.
- The contractor finished installing the corrugated roof decking on the long side and 1 of 2 short sides of canopy B beside the Medical School Building.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor continued installing rectangular supply ductwork and fresh air ductwork for unit 8A and heating water lines for units 8A and 8D in the Clinic Building.
- They started running the main heating water lines for AHU 8A.
- Crews insulated supply ductwork on the 8th Floor.
- The contractor continued installing reheat lines for VAVs in the Administration Building. The contractor has now completed 11 of 14 VAVs.
DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:
- The contractor continues removing old caulk and installing new caulk on the north and east sides of the Clinic Building and on the south side of the Administration Building.