Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, MAY 13, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the metal track for the wood panel system on the 2nd Floor.  
  • The two storefronts for the elevator lobby were delivered and set in place. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor painted the doors and doorframe on the 2nd Floor and touched up paint throughout the 2nd Floor.
  • Crews continued connecting smoke dampers on 2nd Floor of the new building.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor placed the domestic cold water pumps in the 2nd Floor pump room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical wires on the 2nd and 3rd Floors.
  • Workers continued to erect forms for elevator shaft walls in the basement.

CSRB EXHAUST UPGRADE:

  • The contractor relocated the fire sprinklers for Exhaust System #1, #2 and #4.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The abatement contractor installed a collar on the 8th Floor in the hallway and removed ductwork in Room 8312 of the Clinic Building.
  • The contractor continued installing heating water lines for units 8D and pulling wire for unit 8A. 
  • The asbestos contractor removed the heating water insulation in mechanical room 2302 in the Administration Building.     

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued removing the existing caulk from the joints between the exterior wall panels.
  • Crews continued installing new backer rod and caulk on the north and east sides of the Clinic Building and started work on the east side of the Administration Building.