Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, MAY 16, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the metal track for the wood panel system on the 2nd Floor.  
  • Workers continued welding structural steel under the walkway along Bolivar St. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor painted the doors and doorframe on the 1st Floor and touched up paint throughout the 1st Floor.
  • They installed insulation for the louver doors on the 2nd level of the new building.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor began finishing the walls in the housekeeping closet next to the fire pump room.
  • Crews continued setting the domestic water pumps in the 2nd Floor pump room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits on the 2nd and 3rd Floors.
  • They continued to erect forms for elevator shaft wall in the basement.

CSRB EXHAUST UPGRADE

  • The contractor set the roof curb for exhaust system #3.
  • Workers began installing temporary walls on the 2nd Floor.
  • The fire sprinkler heads in the mechanical rooms on the Gravier Street side of the building were relocated.

CEB COVERED WALKWAY:

  • The contractor installed the ice and water guard membrane on canopy B at the end closest to the Clinical Education Building.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating water lines for unit 8A in the Clinic Building.  
  • Crews insulated heating water lines and duct work in mechanical room 2302 in the Administration Building.     

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued to remove the existing caulk from joints between the exterior wall panels.
  • They continued to install new backer rod and caulk on the north and east sides of the Clinic Building and the west side of the Administration Building.