TUESDAY, MAY 17, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the metal track for the wood panel system on the 2nd Floor.  
  • They continued welding structural steel under the walkway along Bolivar St. 
  • Crews began installing formwork and reinforcing for the sloped floor in the new auditorium.
  • Door frames on the 1st Floor were painted.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor repaired the leak in the main fire water supply line on the ground floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor resumed installation of the generator fuel line on the 8th Floor.
  • Door closers were installed on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits on the 3rd Floor.
  • Concrete was poured for the elevator shaft wall in the basement.

CSRB EXHAUST UPGRADE:

  • The contractor applied roofing material for the roof curb for exhaust system #3.
  • Workers began demolishing the ceiling on the 2nd Floor.

CEB COVERED WALKWAY:

  • The contractor began installing the metal roof panels and flashing on canopy B at the end of the walkway closest to the Clinical Education Building.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating water lines for unit 8A in the Clinic Building.
  • Crews insulated the supply duct for AHUs 8A & 8D.  
  • They continued insulating heating water lines and duct work in the Administration Building mechanical room 2302.     

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued to remove the old caulking from the joints between the exterior building panels.
  • They continued installing new caulk on the north and east sides of the Clinic Building and the west side of the Administration Building.