TUESDAY, MAY 24, 2011
ALLIED HEALTH/NURSING BUILDING PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing the metal track for the wood panel system on the 2nd Floor.
- They continued installing the med gas system on the 2nd Floor.
- Workers finished installing the restroom partitions in the Womens restroom on the 1st Floor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor insulated the generator exhaust pipe on the 2nd level of the new building.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing the generator fuel line on the 8th Floor.
- They began installing the controls on the 1st Floor air handling units (AHUs).
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued welding and installing chilled water pipe in the basement.
- They continued installing electrical conduits on the 1st Floor.
- Crews continued removing the elevator shaft in the library area.
- The contractor drove 10 piles (41 of 110) in the Lakeside lot.
CSRB EXHAUST UPGRADE:
- The contractor continued to layout equipment on the roof.
CEB COVERED WALKWAY:
- The contractor finished installing the flashing on canopy B at the end of the walkway closest to the Clinical Education Building.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor continued insulating the supply duct and heating hot water lines for units 8A & 8D in the Clinic Building.
- Crews ran control wires for AHU 8A and 8D.
- The contractor put unit 8C into operation.
- The contractor continued running reheat water lines on the 3rd Floor of the Administration Building.
DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:
- The contractor continued installing new caulk on the north and east sides of the Clinic Building and the west side of the Administration Building.