MONDAY, JUNE 13, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing metal framing for the wood wall panels on the 2nd Floor.
  • Workers continued installing wall framing between the mechanical room and auditorium on the 2nd Floor.
  • The contractor started pre-fabricating the heating hot water lines for the bridge area.       

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor applied epoxy paint on the floor of the C-tower laundry room, the old fire pump room and the old domestic water pump room.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor pressure tested the diesel fuel line on the 1st Floor.
  • The ground wire for the roof-mounted generator was installed.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 3rd Floor.
  • Crews continued demolishing the elevator shaft wall in the basement.
  • The forms for the areaway around the exterior of the Lakeside lot were removed.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for unit 3-B in the Clinic Building. 
  • A CMU block wall was installed between the mechanical room and the Faculty Practice area in the Administration Building.
  • The contractor started installing ceiling grid on the 2nd Floor of the Administration Building. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued to remove old caulk and backer rod from the joints between the exterior building panels and install new caulk and backer rod on the east and west sides of the Clinic Building and the north side of the Administration Building.