Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, JUNE 15, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing metal framing for the wall panels on the 2nd Floor.
  • They continued to pre-fabricate the heating hot water lines for the bridge area.       
  • Crews continued to set toilet fixtures in the 1st Floor restrooms. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor is completing the outstanding punch list items.
  • The project is substantially complete.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to install the ground wire for the generator on the roof.
  • The electrical wires for the fire pump on the 2nd Floor have been terminated.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 3rd Floor.
  • Crews continued to demo the elevator shaft wall in the basement.
  • Workers continued installing drywall along the window wall on the 3rd Floor offices.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor finished installing heating hot water lines for unit 3-B in the Clinic Building and began pressure testing the lines.
  • They started installing chill water lines to the unit 3-B. 
  • The contractor installed supply ductwork for unit 3-B.   

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued installing new caulk on the penthouse, west, and east sides of the Clinic Building and on the north side of the Administration Building.