Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, JUNE 2, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing metal framing for the wall panels on the 2nd Floor.
  • Workers began installing gypsum board the inside of the 2nd Floor classroom.
  • The contractor energized the sliding doors on the 2nd Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued insulating the 4 inch domestic water pipe on the ground floor.
  • They repaired a leak in the domestic water pipe.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the piping manifold for the domestic water pumps.
  • Crews continued installing piping for the fire pump on the 2nd Floor.
  • The contractor began welding the containment pipe for the fuel line.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits and junction boxes on the 3rd Floor.
  • They continued welding and installing 6 inch chilled water pipe in the basement.
  • An additional 8 piles were driving in the Lakeside parking lot.

CSRB EXHAUST UPGRADE:

  • The contractor installed the pipe supports for exhaust fans 3C and 4C.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • Workers continued installing supply ductwork and VAV boxes on the 3rd Floor, unit 3B in the Clinic Building.
  • The contractor insulated the heating hot water pipe in the penthouse.
  • Ceiling tiles were installed in the 8th Floor corridor.
  • The contractor insulated the ductwork for unit L2A in Room 2302 in the Administration Building.

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued installing new caulk on the west and east sides of the Clinic Building and the north side of the Administration Building.