ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued installing the metal framing for the auditorium wall panel system.  

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the fuel line on the 1st Floor.
  • Workers continued wiring the electrical disconnects for the domestic water pumps in the 2nd Floor pump room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 2nd Floor.
  • They removed the concrete forms from the passenger elevator shaft wall in the basement.
  • Crews continued excavating for the pile caps.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for units 3A and 3B in the Clinic Building. 
  • Crews continued installing VAVs and began installing the supply ductwork for unit 3A.
  • The contractor removed unit 3A.  
  • The asbestos contractor removed ductwork near Room 6313. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING:

  • The contractor continued installing new caulk for the columns on the ground floor, the west side the Clinic Building and the north side of the Administration Building.