FRIDAY, JUNE 24, 2011
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 
- The contractor continued installing the metal framing for the auditorium wall panel system.  
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued insulating the piping in the 2nd Floor pump room and welding the fuel line casing on the 1st Floor.
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing electrical conduit on the 2nd and 3rd Floors.
- Workers continued erecting concrete forms for the freight elevator shaft wall in the basement and for the first 3 of 12 pile caps in the Lakeside lot.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor continued installing heating hot water lines and supply ductwork unit 3A in the Clinic Building. 
- Crews placed the concrete pad for unit 3A.
- The asbestos contractor removed ductwork near Room 6405 and in Room 6302. 
- The contractor continued installing sheetrock for the Mens restroom on the 2nd Floor of the Administration Building.