Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JULY 12, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor installed sheetrock for the rear wall of the auditorium.
  • They welded in additional structural supports for the new monumental staircase. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the fuel line casing on the 1st and 8th Floors.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduits on the 2nd Floor.
  • Crews erected the 9th pile cap concrete form in the Lakeside lot.
  • They continued forming the freight elevator shaft wall in the basement.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor began installing new ductwork on the 2nd Floor.
  • They continued installing pitch pockets (roof penetrations for utilities) on the roof for exhaust systems 1 – 4.
  • The contractor began relocating fire alarms and electrical devices on the 2nd Floor.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for unit 6A in the Clinic Building. 
  • Workers are installing supply ductwork for unit 3B. 
  • Crews continued insulating ductwork and heating hot water lines for unit 3A. 
  • They began putting up the ceiling grid up for unit 3A. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued pressure washing the north and east side of the Power Plant.