THURSDAY, JULY 14, 2011
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 
- The contractor continued installing sheetrock for the rear wall of the auditorium.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued welding the fuel line casing on the 1st Floor.
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing conduits on the 2nd Floor.
- Workers continued setting forms and installing steel rebar for 9 of 12 forms for the pile caps in the Lakeside lot.
- The contractor continued forming the freight elevator shaft wall in the basement.
CSRB EXHAUST UPGRADE PROJECT:
- The contractor continued installing ductwork on the 2nd Floor.
- They continued installing roof flashing for exhaust systems 1 and 2.
- The ceiling in Room 729 was removed.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor continued installing heating hot water lines for unit 6A in the Clinic Building. 
- Crews continued installing supply ductwork for unit 3B. 
- The contractor continued insulating ductwork and heating hot water lines for unit 3A and 3B. 
- They removed ceiling tile from Room 3312N. 
- The contractor continued installing the controls for units L2A and L3A in the Administration Building. 
DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:
- The contractor continued pressure washing the north and south side of the Power Plant.