FRIDAY, JULY 15, 2011
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 
- The contractor continued installing sheetrock on the rear wall of the auditorium.
- Floor epoxy was applied to the ramp in the auditorium. 
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued welding the fuel line casing on the 1st Floor.
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing conduits on the 2nd Floor.
CSRB EXHAUST UPGRADE PROJECT:
- The contractor continued installing new ductwork on the 2nd Floor.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor continued installing heating hot water lines for unit 6A in the Clinic Building. 
- They continued installing supply ductwork for unit 3B and 6A. 
- Crews continued insulating ductwork and heating hot water lines for unit 3A and 3B. 
- The contractor installed ceiling tile for unit 3A.
- Workers continued installing the controls for units L2A and L3A in the Administration Building.