ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued framing the monumental stairwell enclosure.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the fuel line casing on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor started installing conduit on the 1st Floor.
  • Crews continued installing the 6 inch domestic waterline in the basement.
  • Workers continued installing forms and rebar in the Lakeside lot.  Formwork completed: 10 of 12; rebar installed: 7 of 12; and concrete poured: 4 of 12.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor lifted all of the new exhaust fans to the roof.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for units 6A and 3A and made the final connections for unit 3B in the Clinic Building. 
  • They continued insulating chilled and heating hot water lines for unit 3A. 
  • The controls contractor installed control wire for units 3A and 3B. 
  • The contractor installed a smoke damper between the 2nd and 3rd Floors of the Administration Building.

DENTAL CAMPUS BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor removed existing caulk and backer rod, prepared the surfaces of the building panels and installed new caulk and backer rod on the east side of the Power Plant.