THURSDAY, JULY 21, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued framing the monumental stairwell enclosure and installed sheetrock near the rear wall of the auditorium.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor.
  • Workers installed metal stud bracing along the corridor wall on the 2nd Floor.
  • The contractor continued installing forms in the Lakeside lot.  Formwork completed: 12 of 12; rebar installed: 9 of 12; and concrete placed: 4 of 12.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor installed utility pitch pockets for exhaust fan sets 1 -4 and set the plenum support for exhaust fan system 10.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing ductwork for air handling unit 6A in the Clinic Building.
  • Crews continued installing heating hot water lines for units 6A and 3A and insulating chilled and heating water lines for unit 3A. 
  • The controls contractor continued installing control wire for units 3A and 3B. 
  • The contractor continued framing the hard ceiling in the Mens restroom on the 3rd Floor. 

DENTAL CAMPUS BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued removing existing caulk and installing new caulk on the east and south sides of the Power Plant.