Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JULY 5, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued installing the metal framing for the auditorium wall panel system.  
  • Workers re-routed the walkway floor drains and installed a check valve on the 1st Floor. 
  • Scaffolding was erected above the monumental stairs. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the fuel line casing on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduits on the 3rd Floor.
  • The first 3 pile caps in the Lakeside lot were poured.
  • Crews continued forming up the 6th and 7th pile caps.
  • The contractor continued forming up the freight elevator shaft wall in the basement.
  • Metal support framing for the corridor wall was installed on the 3rd Floor.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor connected the temporary exhaust ductwork on the 2nd Floor and began to remove the existing exhaust ductwork.
  • Workers welded the exhaust fan frames for exhaust fan systems 1 and 3 on the roof.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines and supply ductwork for unit 3A in the Clinic Building. 
  • They continued to insulate ductwork for unit 3B. 
  • The ceiling grid was installed on the 3rd Floor of the Clinic Building. 
  • The contractor set VAV boxes for AHU 6A.

DENTAL CAMPUS BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued caulking on the west side of the Clinic Building and repaired the loose panels on the south side of the Clinic Building.