FRIDAY, JULY 8, 2011
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 
- The contractor continued prefabricating chilled water lines and installing AV conduit on the 2nd Floor.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued welding the fuel line casing on the 1st Floor.
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing conduits on the 2nd Floor.
- They installed steel rebar for the pile cap nearest to the loading dock in the Lakeside lot.
- Crews continued forming the freight elevator shaft wall in the basement and installing metal support framing for the corridor wall along the 3rd Floor.
CSRB EXHAUST UPGRADE:
- The contractor completed the removal of the exhaust ductwork on the 2nd Floor.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor continued installing heating hot water lines for unit 6A and supply ductwork for unit 3A in the Clinic Building. 
- Workers continued to insulate the ductwork and heating hot water lines for unit 3A. 
- Control wires for unit 3A were installed.
- The contractor installed heating hot water lines for unit L3A in the Administration Building.