Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, AUGUST 1, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor.
  • Workers began installing bracing along the corridor wall on the 1st Floor.
  • They continued installing high pressure steam line in the basement.
  • The contractor began building the concrete forms for the columns that will support the elevated mechanical/electrical enclosure in the Lakeside Lot. 

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor is installing electrical conduit on the 7th Floor to provide power to the exhaust fans located on the roof.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued insulating supply duct and heating hot water lines on the 6th and 3rd Floors of the Clinic Building. 
  • They continued installing heating hot water lines for unit 6A. 
  • Crews taped and floated the sheetrock ceiling in the Men’s restroom on the 6th Floor.  
  • The contractor continued installing supply air duct in the 6th Floor mechanical room. 

DENTAL CAMPUS BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued removing old caulk and installing new caulk on the north and west side of the Power Plant.