MONDAY, AUGUST 1, 2011
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing conduit on the 1st Floor.
- Workers began installing bracing along the corridor wall on the 1st Floor.
- They continued installing high pressure steam line in the basement.
- The contractor began building the concrete forms for the columns that will support the elevated mechanical/electrical enclosure in the Lakeside Lot. 
CSRB EXHAUST UPGRADE PROJECT:
- The contractor is installing electrical conduit on the 7th Floor to provide power to the exhaust fans located on the roof.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor continued insulating supply duct and heating hot water lines on the 6th and 3rd Floors of the Clinic Building. 
- They continued installing heating hot water lines for unit 6A. 
- Crews taped and floated the sheetrock ceiling in the Men’s restroom on the 6th Floor.  
- The contractor continued installing supply air duct in the 6th Floor mechanical room. 
DENTAL CAMPUS BLDG EXTERIOR WATERPROOFING PROJECT:
- The contractor continued removing old caulk and installing new caulk on the north and west side of the Power Plant.