CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 2nd Floor and the steam supply line in the basement.
  • Crews continued removing the concrete forms and back filled for the grade beam in the Lakeside Lot. 

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor placed the fans for exhaust systems #9 and #10 on the fan supports.
  • They continued installing electrical conduit on the 7th Floor to provide power to rooftop exhaust system #3.
  • The installation of the round exhaust ductwork for Phase 2A is progressing.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued insulating the heating hot water line and supply ductwork for unit 6A in the Clinic Building. 
  • Workers continued to run fire alarm wire for units 3A, 3B, and 6A.
  • The demolition of ceilings and lights for unit 5A is underway.