Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, AUGUST 9, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor.
  • They continued installing bracing along the corridor wall on the 1st Floor.
  • Concrete forms are being erected for the grade beams in the Lakeside Lot  

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the exhaust fan platform for exhaust system #10.
  • Crews continued installing electrical conduit on the 7th Floor to provide power to rooftop exhaust system #3.
  • Workers began installing the round exhaust ductwork as part of Phase 2A of the project.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued insulating the heating hot water line for unit 6A in the Clinic Building. 
  • They continued installing fire alarm wire for units 3A, 3B, and 6A.
  • The contractor continued installing control panels and thermostats on the 3rd Floor.