Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, SEPTEMBER 15, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to install conduit in the main lobby of the 1st Floor.
  • Crews continued installing bollards in the parking lot area.
  • The contractor continued working in the elevator pits on elevators 7 & 8.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued plastering the ceiling in the 2nd Floor corridors.
  • Workers are rerouting electrical conduit around exhaust riser #1.
  • The contractor continued insulating the duct riser for exhaust system #4.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor pressure tested the heating water lines on the 5th Floor of the Clinic Building. 
  • Additional ductwork is being installed on the 5th Floor. 
  • The contractor removed the fresh air ductwork connected to the 2nd Floor (Clinic Bldg.) units. 
  • Crews continued insulating the heating hot water lines in the Library and the Bookstore.
  • The contractor installed new fixtures in the Library. 
  • Duct transitions are being installed in the Library.