THURSDAY, SEPTEMBER 15, 2011
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued to install conduit in the main lobby of the 1st Floor.
- Crews continued installing bollards in the parking lot area.
- The contractor continued working in the elevator pits on elevators 7 & 8.
CSRB EXHAUST UPGRADE PROJECT:
- The contractor continued plastering the ceiling in the 2nd Floor corridors.
- Workers are rerouting electrical conduit around exhaust riser #1.
- The contractor continued insulating the duct riser for exhaust system #4.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor pressure tested the heating water lines on the 5th Floor of the Clinic Building. 
- Additional ductwork is being installed on the 5th Floor. 
- The contractor removed the fresh air ductwork connected to the 2nd Floor (Clinic Bldg.) units. 
- Crews continued insulating the heating hot water lines in the Library and the Bookstore.
- The contractor installed new fixtures in the Library. 
- Duct transitions are being installed in the Library.