CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor installed exterior stairs for the new building in the Lakeside lot.
  • They roughed in exterior lighting for the new loading dock area.
  • Crews continued to erect concrete forms for the flood wall in the parking garage.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing exit signs and fire sprinkler heads in the 2nd Floor corridors and cleaning the corridors.
  • Workers continued installing ductwork in Room 722.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor started installing new supply duct on the 2nd Floor of the Clinic Building.
  • They continued insulating heating hot water lines on the 5th Floor. 
  • The installation of the ceilings in the 5th Floor restrooms continues.
  • The heating hot water lines on the 2nd Floor of the Clinic Building were pressure tested.   
  • The contractor completed the 1st phase of the Library renovation.