CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the steel structure for the 3rd level of the new building in the Lakeside lot.
  • Workers continued installing electrical conduits in Room 117 and 117B and erecting concrete forms for the flood wall in the parking garage.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing exit signs and light fixtures in the 2nd Floor corridors.
  • They pulled wiring for the new fan and VFDs for exhaust system #4.
  • Crews installed ductwork in Room 630A.
  • The plaster ceiling was installed in the feed room on the 1st Floor.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor finished insulating the heating hot water lines and supply duct on the 5th Floor of the Clinic Building. 
  • Work continued on the ceiling installation in the 5th Floor restrooms.
  • The contractor continued installing supply duct on the 2nd Floor of the Clinic Building.
  • They started insulating the heating hot water lines on the 2nd Floor.
  • The contractor continued finishing the restroom ceilings on the 3rd Floor of the Administration Building.
  • Crews started moving the Library stacks back into place.