CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing steel structure for the 4th level of the new building in the Lakeside lot and conduits along the 1st Floor corridor.
  • Crews continued removing concrete forms from the flood wall in the parking garage.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the VFDs for exhaust system #1.
  • They continued installing ductwork in Room 412G.
  • The contractor installed the light fixtures in the feed room on the 1st Floor.
  • Workers began repairing the ceiling and walls in Room 729.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing supply and fresh air duct on the 2nd and 5th Floors of the Clinic Building.
  • They continued the ceiling installation in the 2nd and 5th Floor restrooms.
  • The contractor continued installing ceiling grid on the 5th Floor and insulating supply and heating hot water lines on the 2nd Floor. 
  • Control wire for the 5th and 2nd Floors is being run.
  • The contractor abated the 4th Floor, Administration Building mechanical room.
  • They completed the Library move.