Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, SEPTEMBER 6, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the main lobby of the 1st Floor.
  • The elevator car rails for the front passenger elevators are being installed.
  • The contractor is constructing wooden forms and installing steel reinforcement for the flood wall around the parking garage.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing ductwork for exhaust system #9 in Room 342.
  • Workers began plastering the ceiling in the 2nd Floor corridors.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing the heating hot water lines for VAV boxes for unit 5A in the Clinic Building.
  • They continued installing the chilled water lines for unit 5A.
  • The demolition of unit 2A is underway in the Clinic Building.
  • Crews have started installing the VAVs for the new unit 2A. 
  • The contractor continued installing ductwork in the Library.
  • They began installing electrical conduit for the new ceiling layout in the Library.
  • Control wire is being run to the VAVs for unit L3A in the Administration Building.