FRIDAY, SEPTEMBER 9, 2011
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing conduit on the main lobby of the 1st Floor and continued installing the elevator car rails for the front passenger elevators.
- They continued installing formwork for the second section of the flood wall around the parking garage.
 
CSRB EXHAUST UPGRADE PROJECT:
- The contractor continued installing ductwork on the 3rd Floor for Exhaust System #9.
- Workers continued plastering the ceiling in the 2nd Floor corridors.
- Work continued on the installation of the VFDs for exhaust system #10.
- The contractor began insulating the duct risers for exhaust systems# 9 & 10.
 
DENTAL SCHOOL AHU REPLACEMENT PROJECT:    
- The contractor continued installing heating hot water lines for the AHU 5A VAV boxes in the Clinic Building.
- They continued installing VAVs and insulating ductwork for unit 2A in the Clinic Building.
- The contractor poured the concrete pad that will support the new unit 2A.
- Crews finished insulating the new ductwork in the Library.
- The contractor continued installing electrical conduit for the new ceiling layout in the Library.
- Workers continued running the heating hot water lines and control wires to the VAV boxes for unit L3A.