Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, OCTOBER 14, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor poured the concrete deck for the new loading dock.
  • They continued roughing in for exterior light fixtures in the new loading dock area.

CSRB EXHAUST UPGRADE PROJECT:

  • Workers continued installing wiring for the VFDs on the roof for exhaust systems #1, 2, and 4.
  • The contractor began phase 2B of the project by installing the wall and floor protection in the 2nd Floor corridor.

DS CLINIC AHU REPLACEMENT   

  • The contractor continued running heating hot water lines for unit 5B in the Clinic Building. 
  • They pressure tested the new ductwork for unit 5B. 
  • Crews programmed the controls for units 5B and 2A. 
  • The asbestos contractor abated mechanical room 6B in the Clinic Building. 
  • The contractor continued removing ceiling grid for unit 6B. 
  • The concrete pads for units L4C and L4D were poured in the Administration Building.