Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, OCTOBER 3, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor erected the steel framing for the 3rd level of the second bay of the new elevated mechanical/electrical building in the Lakeside lot.
  • They continued installing conduits along the 1st Floor corridor.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor tested the VFDs for exhaust system #9.
  • Ductwork is being installed on the 7th Floor for exhaust system #2.
  • Workers installed ductwork and the ceiling in Room 326.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing supply and fresh air duct on the 5th Floor of the Clinic Building.
  • They continued to install the ceilings in the 2nd and 5th Floor restrooms.
  • The demolition of the old unit 5B is underway.  
  • The contractor continued insulating the chill water lines on the 2nd Floor.
  • The CMU block wall was removed from in front of the Administration Build’s mechanical room that contains units L4C and L4D.