CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued erecting steel framing on the 2nd level of the 2nd bay of the new mechanical/electrical building.
  • They continued installing conduits along the 1st Floor corridor.
  • A waterproof coating was applied to the parking garage flood wall.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the VFDs on the roof for exhaust system #1.
  • Workers started the operational testing of the exhaust fans for the BSL3 lab.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:   

  • The contractor abated mechanical rooms 7A and 7D in the Clinic Building.
  • They continued installing supply ductwork and VAVs for unit 5B.
  • The ceiling installation on the 5th and 2nd Floors is proceeding. 
  • The concrete pad for unit 5B was poured. 
  • The contractor continued demolishing heating hot water lines near units L4C and L4D in the Administration Building.
  • Crews continued removing lights and the ceiling in the Library.