Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, NOVEMBER 1, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to construct the CMU wall for the transformer vault.
  • Conduits are being installed in the 2nd Floor corridor leading to the new MEP building.
  • Workers continued installing the elevator sump pump discharge lines under the 2nd Floor of the MEP building.
  • The contractor continued installing metal decking on the 3rd level of the new MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing conduit for the control system for fan system #10.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:   

  • The contractor continued insulating the heating hot water lines for unit 5B in the Clinic Building.   
  • They continued installing supply ductwork and VAVs for unit 6B.
  • Crews continued installing the heating water lines and transition supply ductwork for unit 7A.
  • The contractor continued installing and insulating the new ductwork in the Library. 
  • Supply and return ductwork is being installed for units L4C and L4D in the Administration Building. 

DENTAL SCHOOL ADMIN BLDG 1ST FL REMEDIATION:

  • The contractor continued removing ductwork and insulation from the 1st Floor.