Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, NOVEMBER 15, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit from the back corridor to the MEP building on the 3rd Floor.
  • Storm drain pipes are being installed on the 2nd level of the MEP building.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued insulating ductwork, installing ductwork transitions, and installing chill and heating hot water lines for unit 6B in the Clinic Building.  
  • Crews continued insulating the chill and heating hot water lines for units 7A and 7D.
  • The demolition of AHUs 6B and 6E is underway. 
  • The contractor continued insulating ductwork and piping in the Library and the 4th Floor Administration Building mechanical room. 
  • They began demolishing the CMU block wall in the mechanical room that houses for units L2B and L3B. 
  • Workers continued to remove piping from units L2B and L3B.  
  • The contractor started installing the new light fixtures in the ceiling of the Library. 
  • Wiring for the VFDs that serve units L4C and L4D is being installed. 

DENTAL SCHOOL ADMIN BLDG 1ST FLOOR ABATEMENT:

  • The contractor completed removing ductwork and insulation on the 1st Floor.