WEDNESDAY, NOVEMBER 23, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit and storm drain pipes on the 3rd level of the MEP building.
  • Crews constructed forms for the roof of areaway #5 on the Gravier St. side of the building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor installed a new motor for fan EF1-2.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for unit 6B in the Clinic Building.  
  • Workers continued insulating the chilled and heating hot water lines for units 7A and 7D.
  • The concrete pad for unit 4A was poured. 
  • The contractor continued installing the ductwork and VAVs for unit 4A.   
  • Crews finished setting units L2B and L3B in place in the Administration Building.   
  • They continued installing the ductwork and VAVs for unit L2B and insulating ductwork for units L4C and L4D. 
  • The contractor completed installing the new ceiling light fixtures and cleaned the Library.