CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 2nd & 3rd levels of the MEP building.
  • They continued installing storm drain pipe on the 3rd level of the MEP building.
  • Crews completed the installation of the exterior limestone panels to cover the window of Room 336.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor installed the temporary exhaust ductwork for phase 2B.

DS CLINIC AHU REPLACEMENT  

  • The contractor poured the concrete pad for unit 2B in the Clinic Building. 
  • Workers continued installing the heating hot water lines, ductwork and VAVs for unit 2B.
  • The contractor installed 34 lights on the 6th Floor. 
  • Crews continued installing the ceiling in the Men’s restroom on the 7th Floor.
  • The contractor continued installing the ductwork transitions for unit L2B and the fire dampers for units L2B and L3B in the Administration Building.   
  • They continued installing heating water lines for unit L2B.  

Human Development Center:

  • The contractor removed an additional 25 old piles.

Resource Center PERMANENT REPAIRS & Mitigation:

  • The contractor is testing the heating water pumps.