CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued fireproofing the structural steel of the MEP building.
  • They continued installing electrical conduit on the 3rd level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The ductwork installed as part of phase 2B passed the pressure test.
  • The contractor began connecting the branch ducts to the new main supply duct.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor began the installation of the heating hot water lines and ductwork for air handling unit 4B in the Clinic Building.
  • The new unit 4B was set in place.
  • Crews continued to install the heating hot water lines for unit 7B.
  • The contractor began setting unit 7C in place. 
  • Workers continued installing control wires and insulating the heating water lines for unit L2B in the Administration Building.
  • The contractor installed ceilings and lights for unit L2B. 

DENTAL SCHOOL ADMIN BLDG FOOD COURT:

  • The contractor continued installing HVAC ductwork in the kitchen area.
  • Crews installed hanger and plumbing pipes in the basement.
  • New conduit was installed in the basement.

HUMAN DEVELOPMENT CENTER:

  • The contractor continued performing the load test for piles.