Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JANUARY 3, 2012

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 3rd level of the MEP building.
  • Crews started working in the elevator pits 1, 2, and 3.
  • Fireproofing material is being applied to the structural steel of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the new ductwork for phase 2B.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor installed critical barriers on the 4th and 7th Floors of the Clinic Building.
  • A chilled water riser was replaced.
  • The air flow on the 6th Floor was balanced.
  • New ductwork is being installed on the 7th Floor.
  • The contractor installed controls and insulated the new ductwork on the 5th Floor.
  • Ceiling tiles are being installed in the 2nd Floor corridor.
  • The new ductwork for units 7B and 7C is being installed.
  • The contractor insulated the heating hot water piping for unit L3B in the Administration Building.
  • Workers insulated the heating hot water and chilled water piping in the L2B/L3B mechanical room.

DENTAL SCHOOL FOOD COURT:

  • The contractor laid out the floor pattern for the terrazzo flooring and began removing the terrazzo.
  • The CMU wall of Room 1104 (service area of the old bookstore) was demolished.
  • The hot water supply and return lines were capped.
  • Crews started to demolish the CMU wall of the telephone room in the basement.

HUMAN DEVELOPMENT CENTER:

  • The contractor continued to setup the jobsite trailer.
  • The top soil was removed from the site and three large (temporary) limestone driveways were installed.
  • The pile driving rig that will be used for the test pile program was set up.