WEDNESDAY, JANUARY 4, 2012

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 3rd level of the MEP building.
  • Work continues in the elevator pits 1, 2, and 3.
  • Crews continued to apply the fireproofing material to the structural steel of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the phase 2B ductwork.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing the ductwork for units 7B and 7C in the Clinic Building.
  • Workers insulated the A-side (Clinic Building) chilled water riser.
  • The heating hot water and chilled water lines for unit 2B are being installed. 

DENTAL SCHOOL FOOD COURT:

  • The contractor finished removing terrazzo flooring.
  • The old telephone room in the basement has been demolished.

HUMAN DEVELOPMENT CENTER:

  • The contractor continued to set up the pile driving rig for the test pile program.