Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, JANUARY 5, 2012

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 3rd level of the MEP building.
  • They continued working in the elevator pits 1, 2, and 3.
  • Crews are fireproofing the structural steel of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the ductwork for phase 2B.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor started installing the VAVs and continued installing the ductwork for units 7B and 7C in the Clinic Building.
  • Workers continued insulating the A-side chilled water riser.
  • The contractor continued installing the heating hot water and chilled water for unit 2B in the Clinic Building. 
  • Crews started insulating the heating hot water lines for unit L2B in the Administration Building.

DENTAL SCHOOL FOOD COURT:

  • The contractor ground the existing terrazzo floor and applied primer where the existing terrazzo floor was removed.

HUMAN DEVELOPMENT CENTER:

  • The contractor continued setting up the pile driving rig for the test pile program.