Chancellor's Notes
February 17, 2006
I'm pleased to report
that this morning the Joint Legislative Committee on the Budget approved
the Louisiana Board of Regents plan to carve out $1 million of the $95
million in federal relief to higher education for incentive grants for New
Orleans residency programs. One hundred grants of $10,000 each will be
awarded to Louisiana natives who graduate from Louisiana medical schools
and match a residency program based at MCLNO. The Regents have also
recommended an additional $4.17 million in relief funding from the same
$95 million pot to LSU Health Sciences Center in New Orleans. While there
has been no specific allocation for current residents, the School of
Medicine is working with the Health Care Services Division to provide an
additional stipend or salary increase. Ill keep you informed as the
effort progresses.
At its meeting
Wednesday, the Public Health and Health Care Committee of the Louisiana
Recovery Authority recommended providing us with $50 million in bridge
funding from a federal Social Services Block Grant. It will go before the
full Authority on Monday at its meeting in Lake Charles which I will
attend. The Committee also recommended $20 million for the Health Care
Services Division.
In the news this week,
among its other stories, our Department of Information Services released
the story of the successful PGY-2 Ophthalmology Match. All eight positions
in the 2006 LSU/Ophthalmology Residency Program Match filled, half in the
programs top ten rank order list, seven of the eight in the programs top
twenty. Significantly, a number of the incoming residents are from
out-of-state. The confidence that these bright young medical professionals
have expressed in the quality of our graduate medical education is
gratifying. And yesterday LSUHSC Emergency Medicine physician Dr. Jim
Aiken, and I briefed media on the regional medical preparations for Mardi
Gras in New Orleans. Dr. Aiken is a leader of the Mardi Gras Planning
Medical Task Force which is a committee of the Greater Metropolitan New
Orleans Health Care Task Force. We had national exposure with both
stories.
Our recovery process is progressing. Here is the
latest update as of February 10th:
The remaining repairs to critical building systems
(fire alarm system, fire pumps, and the electrical system) are nearing
completion in key buildings on the downtown campus. Repairs to the
building elevators continue. Two of the major elevator contractors have
brought in dedicated out of state teams devoted exclusively to LSUHSC to
expedite completion of this process. The repairs to the emergency power
generators that serve the downtown campus buildings are under contract.
The architect/engineering firm responsible for the
Dental School campus has presented proposals that address the temporary
repairs needed to allow occupancy of the upper floors of the two main
buildings, as well as their initial plans for hazard mitigation
(protecting damaged elements of the building from subsequent damage
resulting from a similar event in the future). LSUHSC, FEMA and the
Office of Facility Planning & Control have been pleased with the early
progress. The plans for temporary repairs have been approved and
specifications for that work are being developed now. LSUHSC has been
given permission to use expedited procurement processes to secure
contractors to complete the temporary work.
Work on the environmental remediation contract for
the CSRB, MEB and Lions Eye Center buildings began this week. The
contract requires completion within 30 days of the start of work and
contains penalties for a failure to perform. The contractor is assigning
multiple teams to work in buildings simultaneously. We are optimistic
that this critical body of work will be completed quickly. To minimize
disruption to the research activities that have been restarted in the CSRB,
the contractor has agreed to limit their work to the weekend. We would
appreciate the cooperation of the faculty and staff currently working in
the CSRB in minimizing their time in the buildings during the next two
weekends, so that the contractor can work quickly and without delay.
A second environmental remediation contract will
address the Nursing/Allied Health Building, the Residence Hall, Stanislaus
Hall and the Resource Center. The architect currently anticipates that
work under this contract will begin in about three weeks. Similar
contracts will be issued at later dates to address the Dental School
Clinic and Administration Buildings and 1542 Tulane Ave.
It may be helpful to understand the work that will be
accomplished by the environmental remediation contractors:
- The environmental
remediation process provides for the demolition, removal and disposal of
building materials that were flooded or found to harbor mold spores or
other biological hazards. This is in addition to all of the cleaning
and disposal of flood damage materials that has already been
accomplished through earlier contracts.
- The environmental
readings taken throughout the upper floors of the research buildings
generally showed that the interior spaces were free from mold and other
biological hazards. This allowed us to begin to safely reoccupy the
CSRB and selected spaces in other buildings. In the few rooms/spaces
where readings indicated higher mold levels, the particular rooms or
spaces have been sealed off until the remediation can be completed.
However, the standard protocol for environmental remediation following
the type of flood event that we experienced includes the cleaning,
disinfecting and wipe down processes described below, even when readings
show no evidence of mold or other contaminants. Therefore, the work
being done in the upper floors of the CSRB, Lions Eye Center and the
MEB should not be a cause for concern for any of the faculty and staff
- The standard protocol
for environmental remediation provides for the cleaning and disinfecting
of the interior spaces; wiping down hard surfaces (walls, doors,
stairwells, light fixtures, ceilings, etc.), vacuuming, etc. In the
three research buildings, the cleaning and disinfecting of upper floor
spaces will exclude the research labs, because of the unique conditions
present, but will include hallways, stairwells and other more public
spaces. It includes the Gross Anatomy space and the morgue where
special conditions exist and more robust cleaning and disinfection is
required.
- On the 1st floors where flood water was present, the
demolition will typically include removal of drywall to a height of 7
feet, floor coverings as needed (that were not previously removed by an
earlier contract), ceiling tiles as needed, etc. Removal of asbestos
tiles and the mastic is also included as necessary. Floors and solid
walls (masonry & granite) will be cored to determine if water penetrated
and remediation is required. Metal studs and other structural walls
will initially remain and be cleaned and disinfected. Many metal studs
will require replacement, but that will be done as part of the permanent
repairs. Before the demolition begins, the 1st floor spaces
will be sealed off to prevent migration of any contaminants that may
become airborne during the demolition.
- When completed, the
contract will provide us with unrestricted access to the cleaned spaces
in the upper floors, and spaces on the 1st floors will be
clean and ready for the permanent renovation work.
Telephone Services: Auxiliary Enterprises has been
assessing the telephone services at the various campus buildings. Working
on concert with the States Office of Telecommunications Management (OTM)
and BellSouth the damage is being identified and repairs have begun as
reflected below:
- The testing of BellSouth trunk lines serving the
major buildings has been completed. Repair needs have been identified
and BellSouth is scheduling the needed work.
- The connection panels (demarks) in each building
between the trunk lines and the individual lines feeding the offices and
spaces in the buildings have been inspected. BellSouth has identified
those demarks that they require to be elevated when they are repaired or
reinstalled.
- Where telephone service is currently available to
a building, testing of individual circuits (telephones) will begin.
Where necessary, individual repair tickets will be opened with OTM.
Data Network: Computer Services has been testing
the network infrastructure that connects the data center to the various
downtown campus buildings and provides data circuits to individual
offices, labs, and other spaces.
- The fiber (or cable) that connects each building
has been tested and verified as operable.
- The core switches in each major downtown campus
building have been inspected and proposals to secure new core switches
(where necessary) are being prepared.
- CSRB: The core switches were damaged and must
be replaced. Work is underway on the replacement.
- Lions Eye Center: The core switches were
damaged and must be replaced. The development of a proposal to
replace the switches and (potentially) reinstall it on a higher floor
is underway.
- MEB: The core switches were not damaged by the
flood waters and connectivity can be reestablished as soon as the HVAC
is made available to the telecom closet.
- Residence Hall: Network connectivity is
available to the building.
- Stanislaus Hall: Wireless access point on the
roof was damaged and must be replaced before network connectivity can
be restored.
- Nursing/Allied Health: The network is intact
and connectivity can be re-established as soon as stable electricity
and HVAC are available to the telecom closets.
- Resource Center: The core switches were located
on the 7th floor and were not damaged.
- Dental School Campus: The visual inspection of
the core switches has just begun.
Campus Housing: We appreciate the importance of
making the two campus residence facilities available as quickly as
possible. Particularly in the case of the Residence Hall, the challenges
represented by older building designs and systems are unique and
different. Some of these factors may impact on the time to complete the
work necessary to allow the building to be reoccupied. However,
significant progress has been made in preparing both the Residence Hall
and Stanislaus Hall for reoccupation. For example:
- Both buildings are part of the 2nd
environmental remediation contract that is currently out on bid.
Current plans are to have the contract in place and work underway within
the next three weeks. The Residence Hall is to be the 1st
priority for the contractor.
- Elevator repairs have been underway at both
facilities for some time and continue to be monitored closely.
- The electrical switchgear repairs have been
completed at the Residence Hall. The switchgear at Stanislaus Hall was
not damaged.
- Repairs to the fire pump are underway at the
Residence Hall and are expected to be completed in approximately 2
weeks. The fire alarm panel was not damaged.
- Repairs to the fire alarm system at Stanislaus
Hall have been completed. The fire pump was not damaged.
- The repairs to the emergency generators serving
the downtown campus (including both of these buildings) have been placed
under contract. Work should begin next week.
- Heating and cooling are available in the Residence
Hall. Domestic hot and cold water is also available.
- Heating and cooling are available in Stanislaus
Hall. The domestic (hot and cold) water pump is on order and shipment
of the pump is scheduled for 3/13.
Here are highlights of work that has been
accomplished since our last update was posted on Friday, January 27th.
- The solicitation for a second environmental
remediation contract for the Nursing/Allied Health Building, the
Residence Hall, Stanislaus Hall and the Resource Center has been issued
by the architect. At the direction of the Office of Facility Planning &
Control, they are utilizing an expedited solicitation process, so a
contract award may be made quickly.
- Repair parts for elevators around campus continue
to arrive and the permanent repairs to individual elevators continue.
Two of the major elevator contractors have brought in additional
manpower from out of state to dedicate to completing repairs at the
Health Sciences Center. The elevator contractors continue their work
at:
- CSRB
- MEB
- Lions Eye Center
- Nursing/Allied Health
- Resource Center (two have been certified for
use)
- Stanislaus Hall
- Residence Hall
- Entergy/Gravier St. Garage
Until permanent repairs
are completed and elevators certified by the State Elevator Inspector,
routine use has been discontinued. Restricting the use of elevators in
buildings where the environmental remediation has not been completed will
help to minimize further spreading of mold to upper floors.
- The contractor responsible for cleaning the
restrooms and public areas on the upper portions of the Dental School
Administration and Clinic Buildings has completed the work.
- The emergency removal and disposal of carpet and
other porous & semi-porous materials from basements & 1st floors of the
flooded campus buildings has been completed, except for a small number
of punch list items. Work has been completed at the following
buildings:
- Nursing/Allied Health
- Lions Eye Center
- Resource Center
- CSRB
- MEB
- Stanislaus Hall
- Dental School; 1st floors of the
Administration and Clinic Buildings
- 1542 Tulane Ave.
- The contractor continues to work in the Dental
School basement, where particularly challenging conditions were
present. The removal of the asbestos has now been completed and the
more routine cleaning of the spaces is underway. By early next week, we
anticipate being able to enter the basement without wearing any personal
protective equipment.
- Work continued on the contract to make permanent
repairs to the switchgear in the CSRB, MEB, Lions Eye Center,
Nursing/Allied Health Building and the Residence Hall.
- CSRB: The repairs to the switch gear in the
building have been completed.
- MEB: The last two ground faults (for the A and D
risers) have been replaced. This completes the switch gear repairs at
this building.
- Nursing/Allied Health: The repairs to the
switch gear in the building have been completed.
- Residence Hall: The repairs to the switch gear
in the building have been completed.
- Lions Eye Center: Repair work continues in the
building. A temporary breaker has been installed to allow one main
breaker to be removed and reconditioned.
- School of Dentistry restoration: Regular weekly
meetings with representatives from the architectural/engineering firms,
the Office of Facility Planning & Control, FEMA and LSUHSC have
continued and will remain as a scheduled item for some time.
- The architects/engineers recently presented
revisions to the plan to make temporary repairs to facilitate
reoccupation of the buildings. They received the approval to pursue
this version of the plan which relies on repairing or replacing
critical mechanical and electrical components in the same place that
they originally occupied. LSUHSC has been given permission to utilize
expedited procurement processes to secure the necessary contractors.
- The architects/engineers also presented the
latest plans for permanent repairs and related hazard mitigation,
which were well received by FEMA. Further work on these plans and the
development of cost estimates were encouraged.
- The initial focus for the project continues to
be the rapid design and completion of emergency work necessary to
allow the rapid re-occupation of upper floors of the Administration
and Clinic buildings.
- Downtown campus restoration: Regular weekly
meetings with representatives from the architectural/engineering firms,
the Office of Facility Planning & Control, FEMA and LSUHSC have
continued and will remain as a scheduled item for some time.
- Significant efforts have been made recently to
develop potential options for hazard mitigation. Initial discussions
with FEMA about some of the concepts proposed have occurred and were
well received. We anticipate that a decision between two primary
options for hazard mitigation of the flood damaged animal care spaces
and critical mechanical & electrical systems of several buildings
should be made soon. Once the decision has been made, the architects
& engineers will begin refining their designs/plans and develop the
necessary cost estimates to allow FEMA to more carefully review the
proposal.
- As noted previously, the architects completed
the specifications for the environmental remediation of the
Nursing/Allied Health Building, the Residence Hall, Stanislaus Hall
and the Resource Center. The Office of Facility Planning and Control
have authorized the architect to use an expedited process to secure a
contractor.
- Contracts have been awarded for the repairs to
various types of pumps to supply water and heat to the Residence Hall,
MEB, CSRB, Lions Eye Center, Nursing/Allied Health, and Resource
Center. Parts will be ordered and work is expected to begin on the
repairs shortly. LSUHSC has provided the contractors with the list of
priorities by building for these repairs; however the availability of
some parts may impact on the ability to strictly adhere to the
priorities.
- Work by the contractor responsible for the
permanent replacement of fire pumps in the Nursing/Allied Health Bldg,
the Residence Hall, the Resource Center, the CSRB, the Lions Eye Center
and the MEB continued.
- CSRB: The repairs to the fire pump and fire
alarm system have been completed, tested and passed the inspection by
the State Fire Marshal. As a result, the manual fire watch of the
upper floors is no longer required.
- MEB: The fire pump has been installed and the
required electrical connections made.
- Lions Eye Center: The existing fire pump has
been removed and the new pump has been installed. The concrete pad
has been poured and the pump has been tested. The electrical
connections between the fire pump and the buildings fire alarm system
have been completed.
- Nursing/Allied Health: The existing fire pump
has been removed and the new pump has been installed. The new
concrete pad has been poured. The electrical connections to the pump
motor remain to be completed.
- Resource Center: The existing fire pump has
been removed and the new pump has been installed. The jockey pump
(attached to the fire pump) has also been installed.
- Contracts to repair the fire alarm systems and
their components in downtown campus buildings have been awarded to the
vendors who currently provide annual maintenance to the systems. This
approach will insure that the systems can be re-certified and remain
under the existing maintenance contract. Work continues at this time.
- Stanislaus Hall: The repairs to the system have
been completed and the inspection by the State Fire Marshal has been
performed.
- CSRB: The repairs to the fire alarm system have
been completed and the system has been tested. The State Fire Marshal
has inspected the repaired fire alarm panel and the buildings fire
pump and has allowed the manual fire watch on the upper floors to be
suspended. (See fire pump notes above.)
- MEB: The contractor continues working on repairs
to the fire alarm system at the MEB.
- Lions Eye Center: The repairs to the building
fire alarm system have been completed by LSUHSC Property & Facilities
staff.
- Nursing/Allied Health: The contract has been
awarded for the repairs to the fire alarm system. Work is expected to
being shortly as parts become available.
- Resource Center: The repairs required for the
fire alarm system have been identified and the contract has been
issued.
- A contract has been issued for the repairs to
Animal Care cage washers, bottle washers and sterilizers at the CSRB.
The work on the repairs continues. The steam generators have been
installed and the contract has begun troubleshooting the systems.
Additional problems have been identified with one of the steam
generators and replacement parts are on order and expected early next
week.
- The contract for the repairs to the emergency
generators at the CSRB, MEB, Lions Eye Center, Nursing/Allied Health
Bldg., Resource Center and the Residence Hall has been awarded. Work on
the repairs is expected to begin shortly.
A bid has
been issued for repairs to the medical air compressors, vacuum pumps and
water purifiers at the CSRB, Lions Eye Center and the MEB. Bids were
received on 1/13/06 and have been evaluated. The award recommendation has
been forwarded to the Office of Facility Planning & Control, the Office of
Risk Management and FEMA for their concurrence.
|